Chinese energy company Three Gorges Group (CTG) has completed the first phase of its Dongyuemiao data center project in Yichang, Hubei.
Three Gorges Group | Huawei
The first phase of the project, costing RMB 845 million ($132.7m) and in development since February 2021, measures 40,000 sqm (430, 500 sq ft) with capacity for 4,400 racks. At full build-out, the facility will cover 100,000 sqm (one million sq ft) and host capacity for 26,400 racks across five buildings, deployed in three phases.
The facility, located on the right bank of the Three Gorges Dam area in Yichang City, was built in partnership with Huawei Digital Power. The company provided 160 modular equipment rooms, 38 PowerPODs, 320 SmartLi battery energy storage devices, 160 high-temperature fan walls, one iCooling@AI cooling system, and one ‘AI-Robot’ for inspection uses.